UPM Energy's subsidiary UPM Solar Oy is planning a solar power project in Haukkasuo and Kiikunsuo with co-located battery. The Haukkasuo and Kiikunsuo areas are located east of Kouvola in Utti. The land areas owned by UPM-Kymmene have been previously leased for peat production. According to preliminary plans, it would be possible to build solar power with a total capacity of approximately 500–700 MW in the area.

 
 
Technology
Solar, battery
Status
Under development
Area
700 hectares
 
Capacity
500 - 700 MWp
Project completion
~50%


Phases

Studies

Studies

Land Use Planning

Land Use Planning

EIA

EIA

Permits

Permits

Investment Decision

Investment Decision

OAS = participation and evaluation plan
EIA = YVA

 

Haukkasuo & Kiikunsuo

 
 
 

News and events:

  • Preparation of the EIA Report and Draft Land Use Plan is ongoing

Upcoming public events

  • YVA report and LUP plan: Public events in January 2027, more information to come.

 

Contacts:

Project development, investment decision, land use, agreements

Michael Pfleger
Manager, Wind Business Development
michael.pfleger@upm.com

Communications

Veera Eskelin
Manager, Communications
+358204150705
veera.eskelin@upm.com

 

Project development consultant: studies, project phases: EIA, ym.

Etha Oy: Artturi Kurhela
Technical project manager
 +358 40 554 0735
artturi.kurhela@etha-consultancy.com

 
;